Company schedule is a tab on the Company settings screen.
To have access to Company settings, a user must have the ‘Manage system settings ’ permission enabled in her access level.
The settings are summarized in the table:
Setting | Description |
Treat weekends as workdays | Select the checkbox if you want weekends to be counted as workdays. |
Default number of hours per day | The number that is used for the work hours per day that are set to the personal schedule of a newly created user. Default value is 8. |
Choosing to treat weekends as working days will result in the recalculation of the end dates of all activities.